Location of works: | Don Duong District, Lam Dong Province, Viet Nam | |
Length of Dam: | 280.7m | |
Height of Crest: | 41.78m | |
Main volume of works: | ||
+ Rock & soil excavation: | 151,314,000m3 | |
+ Rock & soil fill: | 12,972 ,000m3 | |
+ CVC works: | 10,010,000m3 | |
Works duration: | ||
+ Commencement: | Quarter 4/2023 | |
+ Completion: | Quarter 1/2026 |