Location of works | :Hoai Nhon District, Binh Dinh Province, Viet Nam | |
Length of Dam | :550m | |
Height of Dam | :17.2m | |
Works duration: | ||
+ Rock & soil excavation | :103,210m3 | |
+ Rock & soil fill | :431,397m3 | |
Works duration: | ||
+ Commencement | :1996 | |
+ Completion | :Dec-1997 |