Green on Trung Son hydropower project
Trung Son hydropower project is located in Trung Son commune, Quan Hoa district, Thanh Hoa province. In the midst of mountains and forests, there are many restrictions on the conditions for recreational activities, but this is not a place where less poetic.Coming to Trung Son hydropower project today is not only the green of mountains and forests but also the living and working environment of its officers and workers are covered with fresh green.
With the hands, the enthusiasm of youth as well as the love for nature of the staffs, engineers and workers at the project site has been creating a green and fresh-airliving environment which sweeping out the sunny, windy and dusty things at the site. The green tree rows are cultivated and fertilized at the worker camps, offices at Trung Son hydropower project to add beauty, freshness and new breath to the life here.
Mr. Le Van Dong – Deputy Project Manager of the Joint Venture of Samsung C&T Corporation and Construction Joint Stock Company No.47 shared “Trung Son hydropower project is implemented to meet the Health – Safety – Environment(HSE) policy of the World Bank (WB), hence, in addition to the construction work, the site environmental management is always taken care of by the Contractor with the supervision and regular advices of the Supervision Consultant, the Employer and experts from the World Bank. Assurance of the green – clean – beautiful environment and landscapes on the site is not only required by the project but also create a harmonious atmosphere on the job site, contributing to the environmental protection, creating the fresh environment for the staffs, engineers and workers on the job site and rest are comfortable” Mr. Dong added.
In addition to planting green trees in the premises of the worker camps and offices, the Contractor has also planted thousands of green trees on the slopes and disposal sites at the areas of the project site to mitigate erosion and landslides, for environmental protection and improvement of the environmental landscape for hydropower construction area “For a sustainable environment”, and that is also the objective of Trung Son Hydropower Project.
Theo trungsonhp.
Conqueringthe weather, advancing the progress at Trung Son hydropower project
Thousands of workers are winning the harshness of weather to construct Trung Son hydropower project in Co Me valley (Trung Son commune, Quan Hoa district, Thanh Hoa province). Not only advance in the progress but also this is a site safety model project.
Arrival atTrung Son Hydropower Project, we plan to go to the construction site as soon as possible when arrived Co Me. Then the sudden afternoon rain caused the car can not move up. The next day morning jump into the car, driver of Trung Son Hydropower Management Board said: must use a special car for mountainous road and the drivingexperiencecan drive on this road, otherwise “you can not move on road” … Indeed, after an hour roughly driven, our car passed a road section less than … 2.5 km from the office of Project Management Board to themain construction site.
In contrast with the remote mountain is a busyand urgent working atmosphere, Phan Thanh Nhan, 29, from Nghe An province, is a worker of Construction Joint Stock Company 47 shared: “I used to work in the construction at dozens of hydropower plants in all over the country, but there is no place with the harsh climate like here. The rain is pouring out, the sun is shining brightly, so the construction of Trung Son hydropower plant met many difficulties, etc”.
Nguyen Trong Luc, a worker who also attached to many hydropower projects, admitted “The weather in Co Me valley is so harsh. There was a day raining from morning to night, there was day withharsh sunny throughout the day. Not to mention, while it is sunny and raining, it is raining and sunny, etc. greatly affect our work”.
Facing the above difficulties, to ensure the progress of construction work and to avoid extreme weather, Mr. Ngo Quoc Phuong, Deputy Director of Trung Son Hydropower Project Management Board said: The Contractor was requested to arrange for workers to work early and leave early (working from 6:30am to 10:30am and 14:00pm to 18:00pm) to ensure the safety on the health of engineers and workers at the job site but ensure the construction progress of the project.
Not just the progress …
In 2013, the works has two main objectives: to complete the flood control task before June 2013 and river blocking to be completed in December 2013. The flood control has been completed before 30 June, and now the job site is under construction ofthe diversion culvert, with the volume of excavation and filling reached 50%. As planned, it will be completed in October, 2013, but with the current progress, the works can reach the target 2 months ahead of schedule.
Observing the whole construction site, there are thousands of workers of Construction Joint Stock Company 47 are excavating rocks, installing rebars and pouring concrete. In particular, each construction team shall include one staff for safety and health care. These staffs are responsible for spending knowledge and checking on occupational safety and health measures to workers before working.
Mr. Nguyen Quang Chinh, AECOM Consultant, Main Supervision Consultant said as the analysis: “Trung Son hydropower project always requiredto comply withthe constructionsafety regulationsstrictly. It can be said that this is a model project of labor safety, environment and livelihood for theresettledpeople. From the commencement day till now, there is noserious accident occurred on the jobsite”.
The gained results are just the beginning, there will be a lot of difficultiesahead. But with efforts of the Employer and the contractors are trying each hour and day to complete the items, bringing the project to the destination on time. (X.Vien – V.Luong)
As reported by Thanhnien.com.vn
Investment for Dinh Binh ecotourism spot
Under approval of Binh Dinh Provincial People Committee about the permittance of CC47 invest and exploit tourism business activities in the Dinh Binh reservoir area at Vinh Hao commune, Vinh Thanh district, Binh Dinh province after constructing Dinh Binh reservoir project to be completed.
CC47 is carrying out survey & detailed plan of this tourism spot. It is expected construction on the basin area of reservoir, with area of over 20 hectares included main sections as: watersport game section, camping section, ecotourism spot, water park; pavilion houses & cabanas. Total capital of project is over 18 bill VND.