Reservoir system of Vinh Son Hydropower Works (Weir C)
Location of construction: K’Bang District, Gia Lai Province Length of crest : 370m Height of crest : 43.5m Main volume: + Rock & soil excavation : 1,014,397m3 + Rock & soil fill : 1,168,979m3 + CVC construction : 3,907m3 Duration of works : + Commencement: October 2003 + Completion : September 2005 |
Construction of Intake and the remaining part of tunnel starting section, chainage Km0÷Km5 – Thuong Kon Tum Hydropower Project
Location: | Dak Tang commune, Kong Plong district, Kon Tum province. | |
Construction of main works:
– Construction of Intake and the remaining part of tunnel starting section, chainage Km0÷Km5. |
||
Construction period: | ||
+ Commencement: | 10/2015 | |
+ Completion: | 04/2018 |
Rolling Weir – A Luoi Hydropower Works
Location of site: | A Luoi District, Thua Thien – Hue Province | |
Length of main weir: | 206.5m | |
Height of main weir crest: | 49.5m | |
Main volume of implementation : | ||
+ Rock & soil excavation: | 1,650,422m3 | |
+ Rock & soil fill: | 107,470m3 | |
+ CVC works: | 137,342m3 | |
Duration of works: | ||
+ Commencement: | The fourth quarter of 2007 | |
+ Completion: | The fourth quarter of 2010 |
Headrace Tunnel of Song Bung 2 Hydropower Project